No 1. Construction Update, On Track for July 2026 Settlements

July 2, 0002

Construction at Stage No. 1 is now complete, and we've been working hard behind the scenes to finalize all the essential approvals and documentation. We're pleased to report that we're now in the final stages before buyers can start building their new homes.

 

Here's where we stand:

 

Construction Complete—April 2026
All infrastructure and home sites are now complete and ready for settlement.

 

Statement of Compliance(SOC) Received— 16 June 2026
A critical approval confirming all construction meets civil engineering standardsand regulations.

 

GAIC Clearance CertificateReceived— 23 June 2026
Confirmation from State Revenue Office that the GrowthAreas Infrastructure Contribution payment for the stage has been paid.

 

Titles in Final Stages—Plan in Pre-Lodgement Check
The Plan of Subdivision has been lodged with Land Registry Victoria. Weanticipate receiving Titles in the week beginning 29 June2026.

 

Settlements Coming Soon—Week Beginning 13 July 2026
Once Titles are received, settlements are anticipated to commence the weekbeginning 13 July 2026.

 

Our team is working diligently to ensure everything is inorder for a smooth settlement process.
We'll be in touch with individual buyerrepresentatives with specific settlement dates and next steps as soon as titlesare received.