Status – In progress
Follow Stage 3 through its six construction phases. Scroll across or use the arrows to see more.
Engineering approvals, authority sign-offs and early site preparation, including clearing, levelling and earthworks.
The official start of works, with machinery brought on site and the construction area established.
Below-ground civil works, including sewer, stormwater drainage, water and gas mains.
Installation of electrical and telecommunications conduits, along with road preparation, laying of asphalt, kerbs, footpaths and driveways.
Council and service authority compliance inspections and sign-offs are undertaken.
Plans are lodged with the Land Titles Office, individual titles are issued and settlement can proceed so building can begin.
Status – Completed October 2026
All six construction phases for Stage 2 are complete. Scroll across or use the arrows to see each one.
Engineering approvals, authority sign-offs and early site preparation, including clearing, levelling and earthworks.
The official start of works, with machinery brought on site and the construction area established.
Below-ground civil works, including sewer, stormwater drainage, water and gas mains.
Installation of electrical and telecommunications conduits, along with road preparation, laying of asphalt, kerbs, footpaths and driveways.
Council and service authority compliance inspections and sign-offs are undertaken.
Plans are lodged with the Land Titles Office, individual titles are issued and settlement can proceed so building can begin.
Status – Completed June 2026
All six construction phases for Stage 1 are complete. Scroll across or use the arrows to see each one.
Engineering approvals, authority sign-offs and early site preparation, including clearing, levelling and earthworks.
The official start of works, with machinery brought on site and the construction area established.
Below-ground civil works, including sewer, stormwater drainage, water and gas mains.
Installation of electrical and telecommunications conduits, along with road preparation, laying of asphalt, kerbs, footpaths and driveways.
Council and service authority compliance inspections and sign-offs are undertaken.
Plans are lodged with the Land Titles Office, individual titles are issued and settlement can proceed so building can begin.